[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143669":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143669,799,1,"单选题","关于工程变更的说法，正确的是（ ）。2017",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","合同实施中，承包人应就合同范围内的业主变更先提出补偿要求",false,{"key":16,"text":17,"correct":14},"B","工程变更的索赔有效期一般为7天，不超过14天",{"key":19,"text":20,"correct":21},"C","工程变更的补偿范围越大，承包人的风险越大",true,{"key":23,"text":24,"correct":14},"D","工程变更索赔期越短，对承包人越有利","本题考查的是施工合同分析的任务。选项A，正确的说法应为“在合同实施中，如果工程师指令的工程变更属于合同规定的工程范围，则承包人必须无条件执行；如果工程变更超过承包人应承担的风险范围，则可向业主提出工程变更的补偿要求”；选项B和选项D，正确的说法应为“工程变更的索赔有效期，由合同具体规定，一般为28天，也有14天的。一般这个时间越短，对承包人管理水平的要求越高，对承包人越不利”。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]