[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143665":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1143665,799,1,"单选题","下列合同实施偏差处理措施中，属于合同措施的是（ ）。2017",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","变更技术方案",false,{"key":16,"text":17,"correct":18},"B","采取索赔手段",true,{"key":20,"text":21,"correct":14},"C","调整工作流程",{"key":23,"text":24,"correct":14},"D","增加经济投入","本题考查的是施工合同实施的控制。合同措施，如进行合同变更，签订附加协议，采取索赔手段等。选项A，属于技术措施。选项C，属于组织措施。选项D，属于经济措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]