[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143664":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1143664,799,1,"单选题","在建设工程施工合同分析时，关于承包人任务的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","应明确承包人的合同标的",true,{"key":16,"text":17,"correct":18},"B","工程变更补偿合同范围以合同金额的一定百分比表示时，百分比值越大，承包人的风险越小",false,{"key":20,"text":21,"correct":18},"C","合同实施中，对工程师指令的变更，承包人必须无条件执行",{"key":23,"text":24,"correct":18},"D","工程变更的索赔有效期越短，对承包人越有利","@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]