[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143642":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1143642,799,1,"单选题","建设工程招标活动中，自投标截止时间到投标有效期终止之前，关于投票文件处理的说法，正确的是( )。（2012）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","投标人可以替换已提交的投标文件",false,{"key":16,"text":17,"correct":14},"B","投标人可以补充或修改已提交的投标文件",{"key":19,"text":20,"correct":14},"C","投标文件在该期间送达的，也应视为有效",{"key":22,"text":23,"correct":24},"D","投标人撤回投标文件的，其投标保证金将被没收",true,"投标担保要确保投标人在投标有效期内不要撤回投标书，因此如果投标人在投标有效期终止之前撤回投标文件，投标保证金将被没收。（所以D正确，） 投标人在投标截止日之前所提交的投标是有效的，超过该日期之后就会被视为无效投标。在招标文件要求提交投标文件的截止时间后送达的投标文件，招标人可以拒收。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]