[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143572":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1143572,799,1,"单选题","施工现场文明施工管理组织的第一责任人（ ）。（2015）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目经理",true,{"key":16,"text":17,"correct":18},"B","总监理工程师",false,{"key":20,"text":21,"correct":18},"C","业主代表",{"key":23,"text":24,"correct":18},"D","项目总工程师","在建立文明施工的组织管理过程中，应确立项目经理为现场文明施工的第一责任人。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]