[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143570":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1143570,799,1,"单选题","根据施工现场环境保护的要求，凡在人口稠密区进行强噪声作业时，须严格控制作业时间。一般情况下，停止强噪声作业的时间上( )。（2013）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","晚9点到次日早4点之间",false,{"key":16,"text":17,"correct":14},"B","晚ll点到次日早4点之间",{"key":19,"text":20,"correct":14},"C","晚10点到次日早5点之间",{"key":22,"text":23,"correct":24},"D","晚10点到次日6点之间",true,"凡在人口稠密区进行强噪声作业时，须严格控制作业时间，一般晚10点到次曰早6点之间停止强噪声作业。 @##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]