[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143444":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1143444,799,1,"单选题","编制安全技术措施计划包括以下工作：①工作活动分类；②风险评价；③危险源识别；④制定安全技术措施计划；⑤评价安全技术措施计划的充分性；⑥风险确定。正确的编制步骤是（ ）。2017",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","①-②-③-④-⑤-⑥",false,{"key":16,"text":17,"correct":14},"B","③-①-②-⑥-④-⑤",{"key":19,"text":20,"correct":14},"C","①-③-⑥-②-⑤-④",{"key":22,"text":23,"correct":24},"D","①-③-⑥-②-④-⑤",true,"本题考查的是安全措施计划制度。编制安全技术措施计划可以按照下列步骤进行：（1）工作活动分类；（2）危险源识别；（3）风险确定；（4）风险评价；（5）制定安全技术措施计划；（6）评价安全技术措施计划的充分性。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]