[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143405":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143405,799,1,"单选题","政府质量监督机构对工程项目实施质量监督的第一步工作是（ ）。 （2015）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","制定质量监督工作计划",false,{"key":16,"text":17,"correct":14},"B","抽查工程质量问题",{"key":19,"text":20,"correct":21},"C","接受建设单位申报手续",true,{"key":23,"text":24,"correct":14},"D","建立工程质量监督方案","对工程项目实施质量监督，应当依照下列程序进行： （一）受理建设单位办理质量监督手续； （二）制订工作计划并组织实施； （三）对工程实体质量和工程质量行为进行抽查、抽测； （四）监督工程竣工验收； （五）形成工程质量监督报告； （六）建立工程质量监督档案。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]