[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143353":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143353,799,2,"多选题","（2019年真题）下列工程质量事故发生的原因中,属于技术原因的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","材料质量检验不严",false,{"key":16,"text":17,"correct":14},"B","盲目抢工",{"key":19,"text":20,"correct":21},"C","施工工艺错误",true,{"key":23,"text":24,"correct":21},"D","结构设计错误",{"key":26,"text":27,"correct":14},"E","台风天气","CD","P189-191 技术原因:指引发质量事故是由于在项目勘察、设计、施工中技术上的失误。例如,地质勘察过于疏略,对水文地质情况判断错误，致使地基基础设计采用不正确的方案 ;或结构设计方案不正确，计算失误,构造设计不符合规范要求;施工管理及实际操作人员的技术素质差,采用了不台适的施工方法或施工工艺等。这些技术上的失误是造成质星事故的常见原因。A属于管理原因;B属于社会、经济原因;E属于人为事故和自然灾害原因。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]