[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143346":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1143346,799,1,"单选题","某基础混凝土试块强度值不满足设计要求，但经法定检测单位对混凝土实体强度进行实际检测后，其实际强度达到堆满允许和设计要求值。正确的处理方式是( )。（2012）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","修补",false,{"key":16,"text":17,"correct":18},"B","不作处理",true,{"key":20,"text":21,"correct":14},"C","返工",{"key":23,"text":24,"correct":14},"D","加固","施工质量事故处理的基本方法包括(一)修补处理(二)加固处理(三)返工处理(四)限制使用(五)不作处理(六)报废处理。 对于法定检测单位鉴定合格的工程，如某检验批混凝土试块强度值不满足规范要求，强度不足，但经法定检测单位对混凝土实体强度进行实际检测后，其实际强度达到规范允许和设计要求值时，可不作处理。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]