[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143307":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1143307,799,1,"单选题","关于单位工程竣工验收的说法，错误的是（）。（2018年真题）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程完工后，总监理工程师应组织各专业监理工程师进行竣工预验收",false,{"key":16,"text":17,"correct":18},"B","工程竣工验收合格后，施工单位应当及时提出工程竣工验收报告",true,{"key":20,"text":21,"correct":14},"C","对存在的质量问题整改完毕后，施工单位应提交工程竣工报告",{"key":23,"text":24,"correct":14},"D","工程竣工质量验收由建设单位负责组织实施","本题考查的是竣工质量验收程序和组织。选项B，正确的表述应为“工程竣工验收合格后，建设单位应当及时提出工程竣工验收报告”。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]