[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143298":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1143298,799,1,"单选题","（2019年真题）装配式混凝土建筑预制构件进场时需检查（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","生产记录",false,{"key":16,"text":17,"correct":18},"B","质量验收记录",true,{"key":20,"text":21,"correct":14},"C","套筒灌浆记录",{"key":23,"text":24,"correct":14},"D","机械连接报告","P183-186 装配式混凝土建筑预制构件进场时应检查质量证明文件或质量验收记录。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]