[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143289":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143289,799,1,"单选题","关于竣工质量验收程序和组织的说法，正确的是（ ）。（2016）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单位工程的分包工程完工后，总包单位应组织进行自检，并按规定的程序进行验收",false,{"key":16,"text":17,"correct":14},"B","工程竣工质量验收由建设单位委托监理单位负责组织实施",{"key":19,"text":20,"correct":21},"C","单位工程完工后，总监理工程师应组织各专业监理工程师对工程质量进行竣工预验收",true,{"key":23,"text":24,"correct":14},"D","工程竣工报告应由监理单位提交并须经总监理工程师签署意见","选项A，正确的说法应为“单位工程中的分包工程完工后，分包单位应对所承包的工程项目进行自检，并应按规定的程序进行验收”； 选项B，正确的说法应为“工程竣工质量验收由建设单位负责组织实施”； 选项D，正确的说法应为“实行监理的工程，工程竣工报告须经总监理工程师签署意见”。 ～199。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]