[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143273":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143273,799,2,"多选题","工程质量验收时，设计单位项目负责人应参加验收的分部工程有（ ）。2017",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","地基与基础",true,{"key":16,"text":17,"correct":18},"B","装饰装修",false,{"key":20,"text":21,"correct":14},"C","主体结构",{"key":23,"text":24,"correct":18},"D","环境保护",{"key":26,"text":27,"correct":14},"E","节能工程","ACE","本题考查的是施工过程质量验收的内容。勘察、设计单位项目负责人和施工单位技术、质量部门负责人应参加地基与基础分部工程验收；设计单位项目负责人和施工单位技术、质量部门负责人应参加主体结构、节能分部工程验收。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]