[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143252":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1143252,799,1,"单选题","（2019年真题）某基坑支护工程采用土钉支护方式，在施工过程质量检测试验时的主要检测试验参数是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","抗拔力",true,{"key":16,"text":17,"correct":18},"B","强身完整性",false,{"key":20,"text":21,"correct":18},"C","墙体强度",{"key":23,"text":24,"correct":18},"D","锁定力","P175-181 本题考查的是工序施工质量控制。施工过程质量检测试验主要内容。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]