[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143244":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143244,799,2,"多选题","建设单位和监理单位组织设计单位向所有的施工单位进行详细的设计交底，其主要目的有( )。（2012）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","深入发现和解决各专业设计之间可能存在的矛盾",false,{"key":16,"text":17,"correct":18},"B","充分理解设计意图",true,{"key":20,"text":21,"correct":18},"C","了解设计内容和技术要求",{"key":23,"text":24,"correct":14},"D","D,消除施工图的差错。解决施工的可行性问题",{"key":26,"text":27,"correct":18},"E","明确质量控制的重点与难点","BCE","建设单位和监理单位应组织设计单位向所有的施工实施单位进行详细的设计交底，使实施单位充分理解设计意图，了解设计内容和技术要求，明确质量控制的重点和难点;同时认真地进行图纸会审，深入发现和解决各专业设计之间可能存在的矛盾，消除施工图的差错。 @##",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]