[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143208":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1143208,799,1,"单选题","施工单位在工程开工前编制的测量控制方案，需经（ ）批准后方可实施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目技术负责人",true,{"key":16,"text":17,"correct":18},"B","项目经理",false,{"key":20,"text":21,"correct":18},"C","总监理工程师",{"key":23,"text":24,"correct":18},"D","项目质量工程师","本题考查的是现场施工准备工作的质量控制。施工单位在开工前应编制测量控制方案，经项目技术负责人批准后实施。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]