[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143206":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143206,799,2,"多选题","根据《建筑工程施工质量验收统一标准》GB 50300-2013，分项工程的划分依据有（ ）。2017",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程部位",false,{"key":16,"text":17,"correct":18},"B","工种",true,{"key":20,"text":21,"correct":18},"C","材料",{"key":23,"text":24,"correct":18},"D","施工工艺",{"key":26,"text":27,"correct":18},"E","设备类别","BCDE","本题考查的是工程质量检查验收的项目划分。分项工程可按主要工种、材料、施工工艺、设备类别等进行划分。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]