[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143199":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1143199,799,1,"单选题","（2020年真题）评价和诊断项目质量控制体系的有效性，一般由（ ）进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目监理单位",false,{"key":16,"text":17,"correct":18},"B","项目管理的组织者",true,{"key":20,"text":21,"correct":14},"C","项目咨询单位",{"key":23,"text":24,"correct":14},"D","第三方认证机构","P161-164 项目质量控制体系的有效性一般由项目管理的组织者进行自我评价与诊断，不需进行第三方认证，其评价的方式不同。选项B正确",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]