[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143188":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143188,799,1,"单选题","（2019年真题）建设工程项目质量管理的PDCA循环中，质量处置 （A）阶段的主要任务是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","明确质量目并标制定实现目标的行动方案",false,{"key":16,"text":17,"correct":14},"B","将质量计划落实到工程项目的施工作业技术活动中",{"key":19,"text":20,"correct":21},"C","对质量问题进行原因分析，采取措施予以以纠正",true,{"key":23,"text":24,"correct":14},"D","对计划实施过程进行科学管理","P159-160 对于质量检查所发现的质量问题或质量不合格，及时进行原因分析，采取必要的措施，予以纠正，保持工程质量形成过程的受控状态。处置分纠偏和预防改进两个方面。前者是采取有效措施，解决当前的质量偏差、问题或事故;后者是将目前质量状况信息反馈到管理部门，反思问题症结或计划时的不周，确定改进目标和措施，为今后类似质盘问题的预防提供借鉴。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]