[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143171":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1143171,799,1,"单选题","建立项目质量控制体系时，首先开展的工作是（ ）。 （2015）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分析质量控制界面",false,{"key":16,"text":17,"correct":14},"B","编制质量控制计划",{"key":19,"text":20,"correct":14},"C","制定质量控制制度",{"key":22,"text":23,"correct":24},"D","确立系统质量控制网络",true,"项目质量控制体系的建立过程，一般可按以下环节依次展开工作： （1）确立系统质量控制网络； （2）制定质量控制制度； （3）分析质量控制界面； （4）编制质量控制计划。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]