[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143162":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143162,799,2,"多选题","建设工程项目质量控制系统运行的约束机制，取决于( )。（2013）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","各质量责任主体对利益的追求",false,{"key":16,"text":17,"correct":14},"B","质量信息反馈的及时性和准确性",{"key":19,"text":20,"correct":21},"C","各主体内部的自我约束能力",true,{"key":23,"text":24,"correct":21},"D","外部的监控效力",{"key":26,"text":27,"correct":14},"E","工程项目管理文化建设的成都","CD","约束机制取决于各主体内部的自我约束能力和外部的监控能力。 @##",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]