[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143161":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143161,799,1,"单选题","项目质量控制体系得以运行的基础条件是（ ）。2017",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目合同结构合理",false,{"key":16,"text":17,"correct":14},"B","组织制度健全",{"key":19,"text":20,"correct":21},"C","人员和资源合理配置",true,{"key":23,"text":24,"correct":14},"D","程序性文件规范","本题考查的是项目质量控制体系的运行。质量管理的资源配置，包括专职的工程技术人员和质量管理人员的配置；实施技术管理和质量管理所必需的设备、设施、器具、软件等物质资源的配置。人员和资源的合理配置是质量控制体系得以运行的基础条件。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]