[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143142":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143142,799,1,"单选题","（2019年真题）下列质量风险应对策略中,属于风险转移策略的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工单位合理安排工期,避开可能发生的自然灾害对质量的影响",false,{"key":16,"text":17,"correct":14},"B","施工单位在施工中有针对性地制定质量事故应急预案",{"key":19,"text":20,"correct":21},"C","建设单位在工程发包时,要求承包单位提供履约担保",true,{"key":23,"text":24,"correct":14},"D","建设单位在工程预算价格中预留一定比例的不可预见费","P154-158 A属于风险规避; B属于风险减轻; D属于风险自留。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]