[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143118":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143118,799,2,"多选题","（2020年真题）下列建设工程项目进度控制措施中，属于技术措施的有（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","分析装配式混凝土结构和现浇混凝土结构对施工进度的影响",true,{"key":16,"text":17,"correct":18},"B","采用网络计划技术优化工程施工工期",false,{"key":20,"text":21,"correct":18},"C","分析无粘结预应力混凝土结构的技术风险",{"key":23,"text":24,"correct":14},"D","通过比较钢网架高空散装法和高空滑移法的优缺点选择施工方案",{"key":26,"text":27,"correct":14},"E","通过变更落地钢管脚手架为外爬式脚手架缩短工期","ADE","P147 技术措施涉及对实现进度目标有利的设计技术和施工技术的选用。 BC属管理措施。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]