[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143116":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1143116,799,1,"单选题","（2020年真题）下列建设工程项目进度控制措施中，属于经济措施的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","增加进度控制的岗位和人员",false,{"key":16,"text":17,"correct":18},"B","编制资源需求计划",true,{"key":20,"text":21,"correct":14},"C","比较分析工程物资的采购模式",{"key":23,"text":24,"correct":14},"D","分析施工技术的先进性和经济合理性","P147 建设工程项目进度控制的经济措施涉及资金需求计划、资金供应的条件和经济激励措施等。为确保进度目标的实现，应编制与进度计划相适应的资资金需求计划（资源进度计划），包括资金需求计划和其他资源（人力和物力资源）需求计划，以反映工程实施的各时段所需要的资源。B选项正确。A为组织措施，C为管理措施，D为技术措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]