[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143110":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143110,799,2,"多选题","（2019年真题）下列项目进度控制的措施中，属于经济措施的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","编制工程网络计划",false,{"key":16,"text":17,"correct":18},"B","编制资源需求计划",true,{"key":20,"text":21,"correct":14},"C","分析影响进度的资源风险",{"key":23,"text":24,"correct":18},"D","采取激励措施",{"key":26,"text":27,"correct":18},"E","分析资金供应条件","BDE","P147 建设工程项目进度控制的经济措施涉及资金需求计划、资金供应的条件和经济激励措施等。为确保进度目标的实现，应编制与进度计划相适应的资源需求计划(资源进度计划) ，包括资金需求计划和其他资源(人力和物力资源)需求计划，以反映工程实施的各时段所需要的资源。通过资源需求的分析，可发现所编制的进度计划实现的可能性，若资源条件不具备，则应调整进度计划。资金需求计划也是工程融资的重要依据。 资金供应条件包括可能的资金总供应量、资金来源(自有资金和外来资金)以及资金供应的时间。在工程预算中应考虑加快工程进度所需要的资金，其中包括为实现进度目标将要采取的经济激励措施所需要的费用。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]