[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143108":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143108,799,2,"多选题","下列建设工程项目进度控制措施中，属于管理措施的有（ ）。（2015）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","选择合同结构",true,{"key":16,"text":17,"correct":14},"B","分析工程风险",{"key":19,"text":20,"correct":21},"C","建立管理组织体系",false,{"key":23,"text":24,"correct":14},"D","确定物资采购模式",{"key":26,"text":27,"correct":21},"E","明确管理职能","ABD","内容较多，最好翻书看，做标记。 选项CE属于组织措施。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]