[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143106":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143106,799,1,"单选题","下列建设工程项目进度控制的措施中，属于技术措施的是( )。（2012）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","确定各类进度计划的审批程序",false,{"key":16,"text":17,"correct":14},"B","选择合理的合同结构",{"key":19,"text":20,"correct":21},"C","优选工程项目施工方案",true,{"key":23,"text":24,"correct":14},"D","选择工程承发包模式","技术措施：施工方案对工程进度有直接的影响，在决策其选用时，不仅应分析技术的先进性和经济合理性f 还应考虑其对进度的影响。在工程进度受阻时，应分析是否存在施工技术的影响因素，为实现进度目标有无改变施工技术、施工方法和施工机械的可能性。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]