[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143104":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143104,799,1,"单选题","为实现进度目标面采取的经济激励措施所需要的费用，应在( )中考虑。（2012）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","投标报价",false,{"key":16,"text":17,"correct":14},"B","投资估算",{"key":19,"text":20,"correct":21},"C","工程预算",true,{"key":23,"text":24,"correct":14},"D","工程概算","经济措施是指实施进度计划的资金保证措施，涉及资金需求计划、资金供应条件和经济激励措施等。在工程预算中应考虑加快工程进度所需要的资金，其中包括为实现进度目标将要采取的经济激励措施所需要的费用。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]