[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143102":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143102,799,2,"多选题","下列进度控制的措施中，属于经济措施的有( )。（2012）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","按时支付工程款项",true,{"key":16,"text":17,"correct":14},"B","设立提前完工奖",{"key":19,"text":20,"correct":14},"C","拖延完工予以处罚",{"key":22,"text":23,"correct":24},"D","编制进度控制工作流程",false,{"key":26,"text":27,"correct":24},"E","选用恰当的承发包形式","ABC","经济措施主要是涉及资金需求、资金供应和经济激励等的措施，ABC符合题意。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]