[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143100":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1143100,799,1,"单选题","为赶上已拖延的施工进度，项目部决定采用混凝土泵代替原来的塔吊运输混凝土。该纠偏措施属于（ ）。 （2015）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","管理措施",false,{"key":16,"text":17,"correct":14},"B","组织措施",{"key":19,"text":20,"correct":14},"C","经济措施",{"key":22,"text":23,"correct":24},"D","技术措施",true,"建设工程项目进度控制的技术措施涉及对实现进度目标有利的设计技术和施工技术的选用。 施工方案对工程进度有直接的影响，在决策其选用时，不仅应分析技术的先进性和经济合理性，还应考虑其对进度的影响。在工程进度受阻时，应分析是否存在施工技术的影响因素，为实现进度目标有无改变施工技术、施工方法和施工机械的可能性。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]