[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143096":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1143096,799,1,"单选题","下列进度控制措施中，属于组织措施的是（）。 （2014）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","编制工程网络进度计划",false,{"key":16,"text":17,"correct":14},"B","编制资源需求计划",{"key":19,"text":20,"correct":14},"C","编制先进完整的施工方案",{"key":22,"text":23,"correct":24},"D","编制进度控制的工作流程",true,"选项A属于管理措施。选项B属于经济措施。选项C属于技术措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]