[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143094":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143094,799,2,"多选题","项目进度控制时，进度控制会议的组织设计的内容有（）。（2014）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","会议的具体流程",false,{"key":16,"text":17,"correct":18},"B","会议的类型",true,{"key":20,"text":21,"correct":18},"C","会议的支持人",{"key":23,"text":24,"correct":18},"D","会议的召开时间",{"key":26,"text":27,"correct":18},"E","会议文件的整理","BCDE","进度控制工作包含了大量的组织和协调工作，而会议是组织和协调的重要手段，应进行有关进度控制会议的组织设计，以明确： ( 1 ) 会议的类型； ( 2 ) 各类会议的主持人及参加单位和人员； ( 3 ) 各类会议的召开时间； ( 4 ) 各类会议文件的整理、分发和确认等。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]