[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143086":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143086,799,2,"多选题","下列进度控制的措施中，属于组织措施的有( )。（2013）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","选择承发包模式",false,{"key":16,"text":17,"correct":14},"B","进行工程进度的风险分析",{"key":19,"text":20,"correct":21},"C","编制项目进度控制的工作流程",true,{"key":23,"text":24,"correct":14},"D","落实资金供应的条件",{"key":26,"text":27,"correct":21},"E","进行有关进度控制会议的组织设计","CE","AB属于管理措施，D属于经济措施。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]