[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143084":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143084,799,1,"单选题","建设工程项目进度控制的措施中，“定义项目进度计划系统的组成”属于（ ）措施。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","管理",false,{"key":16,"text":17,"correct":14},"B","经济",{"key":19,"text":20,"correct":21},"C","组织",true,{"key":23,"text":24,"correct":14},"D","技术","本题考查的是项目进度控制的组织措施。“定义项目进度计划系统的组成”属于项目进度控制的组织措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]