[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143082":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143082,799,2,"多选题","下建设工程项目进度控制的措施中，属于管理措施的有（ ）。2017",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","采用工程网络计划实现进度控制科学化",true,{"key":16,"text":17,"correct":18},"B","明确进度控制管理职能分工",false,{"key":20,"text":21,"correct":14},"C","选择合理的工程物资采购模式",{"key":23,"text":24,"correct":18},"D","编制资源需求计划",{"key":26,"text":27,"correct":14},"E","重视信息技术在进度控制中的应用","ACE","本题考查的是项目进度控制的管理措施。选项B，属于组织措施。选项D，属于经济措施。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]