[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143068":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1143068,799,1,"单选题","（2020年真题）双代号网络计划中，某工作最早第3天开始，工作持续时间2天，有且仅有2个紧后工作，紧后工作最早开始时间分别是第5天和第6天，对应总时差是4天和2天。该工作的总时差和自由时差分别是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3天，0天",true,{"key":16,"text":17,"correct":18},"B","0天，0天",false,{"key":20,"text":21,"correct":18},"C","4天，1天",{"key":23,"text":24,"correct":18},"D","2天，2天","P130-142 总时差等于其最迟开始时间减去最早开始时间，或等于最迟完成时间减去最早完成时间。总时差=min{5+4-2，6+2-2}-3=3。 自由时差等于紧后工作的最早开始时间减去本工作的最早完成时间。自由时差=min{5，6}-（3+2）=0。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]