[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143066":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1143066,799,1,"单选题","（2020年真题）关于双代号时标网络计划的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","时间坐标系方向可以垂直向上",false,{"key":16,"text":17,"correct":18},"B","节点中心必须对准相应时标位置",true,{"key":20,"text":21,"correct":14},"C","可以用水平虚箭线表示虚工作",{"key":23,"text":24,"correct":14},"D","时间坐标必须是日历坐标体系","P118-129 A错误，时标网络计划中所有符号在时间坐标上的水平投影位置，都必须与其时间参数相对应。节点中心必须对准相应的时标位置。B正确 C错误，时标网络计划中虚工作必须以垂直方向的虚箭线表示，有自由时差时加波形线表示。 D错误，时标的时间单位应根据需要在编制网络计划之前确定，可为时、天、周、月或季。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]