[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143040":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143040,799,2,"多选题","（2019年真题）关于网络计划中工作自由时差（FFi或ij）说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","自由时差是在不影响工期的前提下，工作所具有的机动时间",false,{"key":16,"text":17,"correct":18},"B","FFi=min{LAGij}（LAGij是本工作和紧后工作之间的间隔时间）",true,{"key":20,"text":21,"correct":14},"C","FFij=min{ESjk-EFjk}（ESjk是所有紧后工作的最早开始时间）",{"key":23,"text":24,"correct":18},"D","FFij=min{ETj}-ETi -Dij(ETj是指所有紧后工作开始节点的最早时间)",{"key":26,"text":27,"correct":18},"E","时标网络计划中，自由时差是该工作与紧后工作间最短波形线的长度","BDE","P130-142 自由时差是指在不影响其紧后工作最早开始的前提下，工作可以利用的机动时间，A错误。 C选项应该为FFij=min{ESjk-EFij}即紧后工作最早开始时间-该工作最早完成时间。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]