[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143037":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143037,799,1,"单选题","（2019年真题）关于单代号网络计划绘图规则的说法，正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不允许出现虚工作",false,{"key":16,"text":17,"correct":14},"B","箭线不能交叉",{"key":19,"text":20,"correct":21},"C","不能出现双向箭头的连线",true,{"key":23,"text":24,"correct":14},"D","只能有一个起点节点，但可以有多个终点节点","P118-129 单代号网络图中,当网络图中有多项起点节点或多项终点节点时,应在网络图端分别设置一项虚工作,作为该网络图的起点节点( St)和终点节点(Fin ),A选项错误； 绘制网络图时,箭线不宜交叉，当交叉不可避免时,可采用过桥法或指向法绘制，B错误。 单代号网络图中只应有一个起点节点和一个终点节点， D错误。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]