[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143031":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1143031,799,1,"单选题","（2019年真题）某装饰工程共有墙纸裱糊、墙面软包两项相互独立的施工过程,每项施工过程包括备料、运输、现场施工三项工作,墙纸裱糊各项工作的持续时间分别为2、1、6天，墙面软包各项工作的时间分别是3、2、4天;由于运输工具的限制,每天只能运输一项施工过程的材料，该装饰工程的最短施工工期是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","9",true,{"key":16,"text":17,"correct":18},"B","10",false,{"key":20,"text":21,"correct":18},"C","11",{"key":23,"text":24,"correct":18},"D","12","P118-129 最短施工工期为：2+1+6=9天。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]