[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143027":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":21,"analysis":22},1143027,799,1,"单选题","由分部工程双代号网络计划如下图所示，则工作C的自由时差为（ ）天。 （2013）",[11,15,18],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","2",{"key":19,"text":20,"correct":14},"C","3","","根据自由时差公式，FFij=ESjk-ESij-Dij=6-0-6=0@##",{"id":6,"name":24,"category":25,"favorite":26},"一建建设工程项目管理","建筑工程",0]