[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143026":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":22},1143026,799,1,"单选题","某工作间逻辑关系如下图，则正确的是（ ）。2017 A: A、B均完成后同时进行 C、D B: A、B均完成后进行D C: A、",[11,15,19],{"key":12,"text":13,"correct":14},"A","C均完成后同时进行",false,{"key":16,"text":17,"correct":18},"B","E",true,{"key":20,"text":21,"correct":14},"C","C完成后进行E","本题考查双代号网络计划中的各种工作的逻辑关系。A 选项中，A、B 工作均完成后进行D 工作，C 工作与AB 工作没有先后逻辑关系。A 选项错误。ABC 工作均完成后，E 工作才能开始，D 选项错误。@##",{"id":6,"name":24,"category":25,"favorite":26},"一建建设工程项目管理","建筑工程",0]