[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143016":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1143016,799,1,"单选题","根据下列逻辑关系表绘制的双代号网络图如下图所示，其存在的错误是( )。（2012）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","节点编号不对",false,{"key":16,"text":17,"correct":18},"B","有多个终点节点",true,{"key":20,"text":21,"correct":14},"C","逻辑关系不对",{"key":23,"text":24,"correct":14},"D","有多个起点节点","双代号网络图只能有一个起点和一个终点，而由图可知8、9均为终点，错误。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]