[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143014":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1143014,799,1,"单选题","关于进度计划调整的说法，正确的是( )。（2012）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","网络计划中某项工作进度超前，不需要进行计划的调整",false,{"key":16,"text":17,"correct":14},"B","非关键线路上的工作不需进行调整",{"key":19,"text":20,"correct":14},"C","当某项工作实际进度拖延的时间超过其总时差时，只需考虑总工期的限制条件",{"key":22,"text":23,"correct":24},"D","根据计划检查的结果在必要时进行计划的调整",true,"当关键线路的实际进度比计划进度提前时，若不拟提前工期，应选用资源占用量大或者直接费用高的后续关键工作，适当延长其持续时间，以降低其资源强度或费用，A错; 网络计划调整的内容包括调整非关键工作时差，B错; 当一项工作出现问题时，需要考虑其对其他工作的影响，C错。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]