[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142991":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142991,799,1,"单选题","已知工作F有且仅有两项并行的紧后工作G和 H，G工作的最迟开始时间为第12天，最早开始时间为第8天；H工作的最迟完成时间为第14天，最早完成时间为第12天；工作F与 G、H的时间间隔分别为4天和5天，则F工作的总时差为（ ）天。 （2015）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0",false,{"key":16,"text":17,"correct":14},"B","5",{"key":19,"text":20,"correct":21},"C","7",true,{"key":23,"text":24,"correct":14},"D","9","",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]