[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142967":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142967,799,1,"单选题","关于关键工作和关键线路的说法正确的是（）。（2014）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","关键线路上的工作全部是关键工作",true,{"key":16,"text":17,"correct":18},"B","关键工作不能再非关键线路上",false,{"key":20,"text":21,"correct":18},"C","关键线路上不允许出现虚工作",{"key":23,"text":24,"correct":18},"D","关键线路上的工作总时差均为零","选项B非关键线路上也有可能有关键工作； 选项C关键线路上允许有虚工作； 选项D应为“总时差为0的工作为关键工作”。如果计划工期大于计算工期，那么关键线路上的总时差＝计划工期－计算工期",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]