[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142964":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142964,799,1,"单选题","某工程双代号时标网络计划如下图（时间单位：天），工作A的总时差为（ ）天。（2015）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0",false,{"key":16,"text":17,"correct":18},"B","1",true,{"key":20,"text":21,"correct":14},"C","2",{"key":23,"text":24,"correct":14},"D","3","本题考查的是双代号网络计划时间参数的计算。双代号时标网络中的总时差等于本工作的自由时差加上后续线路中波形之和的最小值，所以A的总时差为1。 换个角度，总时差的定义就是工作不影响总工期，A不影响关键线路的F，就不影响总工期了，一天时间。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]