[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142961":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142961,799,2,"多选题","某分部工程双代号网络划如下图所示，其存在的绘图错误有( )。（2013）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","多个终点节点",false,{"key":16,"text":17,"correct":18},"B","多个起点节点",true,{"key":20,"text":21,"correct":18},"C","节点编号有误",{"key":23,"text":24,"correct":14},"D","存在循环回路",{"key":26,"text":27,"correct":18},"E","有多余虚工作","BCE","有多个起点节点①和③；有两个⑧节点和节点指向错误③→②，故节点编号错误；有多余虚工作③→②和③→④，节点⑨→⑩。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]